Project Background
The power energy station is equipped with a 2MW gas internal combustion engine coupled with a flue gas/hot water-driven lithium bromide absorption chiller and other auxiliary equipment. All generated electricity is fed into the grid, while any shortfall in cooling capacity from the absorption chiller is supplemented by electric refrigeration units. The system achieves an annual comprehensive energy utilization rate of >85%.
Project Location:
Xinmi, Henan
Equipment Provided:
1*CG170-20/2000KW/10.5KV
Commissioning & Service:
Commissioned in late 2020 / Self-consumption with surplus electricity fed into the grid